Fixed price vs time and materials: start with the knowns
Fixed price vs time and materials changes what you can agree in advance and how you manage spending. Start by asking how much of the work you can describe and check today. If the result is clear and stable, a fixed price may fit. If important answers are missing, a short, controlled period of time and materials may help you learn before you commit.
A fixed price normally sets a fee for an agreed scope. Time and materials usually charges for actual work at agreed rates, plus any agreed expenses. Neither label tells you what is included, who can approve changes or when work stops. Those details need to be clear in the proposal and agreement.

What a fixed price can and cannot tell you
Ask the supplier to describe the task from start to finish. List the people who will use it, the systems it must connect to and the result each person needs. Agree how you will check that each part works. A price is easier to compare when both quotes cover the same outcome.
Check what happens when a request falls outside that scope. A fixed fee can give you a known price for the agreed work, but a change may need a new quote and approval. It does not make an unclear requirement clear. It may also include room for the supplier to cover risk. Ask what assumptions sit behind it.
This model can be a poor fit if you have not yet seen the existing system, checked its data or agreed which users need access. A supplier may have to guess. A low headline price can then lead to a difficult discussion when those guesses turn out to be wrong.
How time and materials works
You pay for time spent at the agreed rates and for any expenses that the agreement allows. This can give you room to change the order of work as you learn. It also means the final total may change, so the buyer needs a way to see progress and make decisions.
Ask for a named person who can approve work, an ordered list of tasks and a regular report of time and results. Agree how often you will review the plan. Ask the supplier to flag likely overruns early, before the next spend is committed.
A spending limit is useful only if its terms say what happens when it is reached. Does work stop, or does it continue after a new approval? Is the limit a firm cap, an estimate or a warning point? Put the answer in writing and agree how unused time, expenses and taxes are treated.
A worked example with two proposals
Imagine a service firm wants a simple booking tool. The same release includes a booking form, a staff view and a confirmation email. Both proposals exclude third-party subscription fees and tax for this comparison. The amounts are fictional and apply only to this example.
Supplier A offers a fixed fee of £12,000 for that agreed release. Supplier B estimates 30 days at £400 per day. The estimate is also £12,000 because 30 multiplied by £400 equals £12,000. If B needs 35 billable days at the same rate and there is no binding cap, the work would cost £14,000 before excluded charges.
If the firm adds a payment feature, A may treat it as a change to the agreed scope. B may put it on the list, but the extra work can use more days. Ask both suppliers to price and approve that change before it starts. The fixed proposal does not guarantee that every future request is included, and the estimate does not guarantee the work will finish in 30 days.
Now suppose the firm has a £12,000 cap for supplier time. Under B’s proposal it can ask for a written stop at that amount and review what is complete before more work is agreed. That does not ensure the full release will be finished within the limit. The agreement should state who can approve any further spend.
A simple decision check
Choose a fixed scope for a defined outcome when the key journeys, data and checks are known. Before signing, ask for the exclusions, the review steps and a clear way to price a change. Check that you can provide the decisions and materials the supplier depends on.
Consider a short time and materials stage when a key answer is missing. Set a time limit, a spend limit and a question to answer. For example, can the old booking data be moved safely? Ask for a written finding and a plan before deciding whether to proceed.
You can combine approaches. Pay for a bounded discovery stage, then agree a fixed scope for a defined build. Or use small fixed outcomes alongside a controlled allowance for uncertain work. A hybrid is only useful when the boundary between the two parts is clear.
Questions to ask before you choose
Ask each supplier to name the result, the assumptions and what is excluded. Who approves changes? How are delays or extra days raised? What can you see at each review, and who checks it? What happens to the source code, data and access if the work ends?
Also ask what happens after launch. Hosting, other services, fixes and support may be outside the build quote. Compare those items on the same basis. Keep a record of the decisions and ask for advice on the agreement when you need it.
UK government guidance on digital buying recommends matching the commercial approach to the work and its uncertainty. It is written for public-sector buyers. Private buyers can use its questions to compare proposals and seek advice on their own agreement. The right next step is to compare both proposals against one written outcome, then settle the open assumptions before approving work.